Hello,

I am struggling with trying to combine the calendar view with a custom
filter I created in MS-project 2003.

My filter is by task name and needs to include a few summary tasks, so I can
show a some activities that span multiple days. Unfortunately, Calendar view
will not display them. Is there any way to get around this? I searched this
community and tried some suggestions but they didn't work.

Any help would be appreciated.

Thanks,
 
C

Chris Marriott

Hi Tina

The issue is not with the filter it is with the formatting of the summary
bars in the calendar view

Summary bars are not shown in the calendar view by default

To see summary bars - Select the format menu and click on bar styles

In the task type list, the summary bar style is currently set to none

Choose how you want it displayed and your calendar view & filter should then
work.

I hope this helps.


--
Regards


Chris Marriott
UK - EPM Consultant & Trainer
 