In the View menu choose Tables. Among the tables listed in the menu you'll
find baseline information in the Cost, Tracking, Variance, and Work tables.
If you select More Tables at the bottom of the list you'll find a library of
additional tables and many of them include baseline data as well. Finally
you can customize any table or completely roll your own and you'll find many
baseline fields in the list of available columns you can use.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs