Dear all,
assuming, I have an early version of a Project Plan with only planned
values inside. Of this plan, I safe a baseline.
No the project plan "lives" meaning:
1) actual costs of tasks completed are entered
2) later tasks are refined and planned in more detail
I would like to have a comparison with a baseline, which contains only
my planned values.
As soon, as I enter actual values and safe a new baseline because I
added new tasks, the planned costs or finished tasks are replaced by the
actual values.
How do I get a comparison with my original planning costs, after I have
to add tasks to a baseline?
Thanks and cheers,
Riko
assuming, I have an early version of a Project Plan with only planned
values inside. Of this plan, I safe a baseline.
No the project plan "lives" meaning:
1) actual costs of tasks completed are entered
2) later tasks are refined and planned in more detail
I would like to have a comparison with a baseline, which contains only
my planned values.
As soon, as I enter actual values and safe a new baseline because I
added new tasks, the planned costs or finished tasks are replaced by the
actual values.
How do I get a comparison with my original planning costs, after I have
to add tasks to a baseline?
Thanks and cheers,
Riko