S
Steve268
Hi,
as with a few others, my post has disappeared so im reposting the text, and
responses so far from my query.
Would be really grateful of any further help on this !
Thanks
Steve
..............................................................
Fair Point Jan !!
I want to be able to calculate the difference in dates between tasks and
show the
output in a filed next to the task.
For example Task ID 100 - Project Meeting 1/1/07
Taks ID 320 Project update 5/1/7
(Linked through various levels of predecessors to Task 120 not directly
linked)
So a custom field is required next to the tasks to show that there are 4
days between tasks 100 and 320.
I understand that using VB this would not be dynamic, in that the coding
would have to state the task id's and would need to be changed for each
calculation needed, but this is fine.
There are only 3 key milestones that i need to look at for this, so whilst
it will not be a well used field, it's content is still worthwhile.
Thanks
Steve
as with a few others, my post has disappeared so im reposting the text, and
responses so far from my query.
Would be really grateful of any further help on this !
Thanks
Steve
..............................................................
Fair Point Jan !!
I want to be able to calculate the difference in dates between tasks and
show the
output in a filed next to the task.
For example Task ID 100 - Project Meeting 1/1/07
Taks ID 320 Project update 5/1/7
(Linked through various levels of predecessors to Task 120 not directly
linked)
So a custom field is required next to the tasks to show that there are 4
days between tasks 100 and 320.
I understand that using VB this would not be dynamic, in that the coding
would have to state the task id's and would need to be changed for each
calculation needed, but this is fine.
There are only 3 key milestones that i need to look at for this, so whilst
it will not be a well used field, it's content is still worthwhile.
Thanks
Steve