A
Alan
In my environment, we are asked to provide status of a project based on how
many days ahead/behind the baseline we are at a given point. I was wondering
if there is a quick way to determine/calculate this figure. I have tried
several things, but wanted a sanity check on the best method.
Project info
I have set up the project so that everything rolls up to a single summary
line. Based on specific constraints, links, and durations inputed, the dates
are scheduled by Project. I have established a baseline and we are tracking
completion of individual tasks under the actual start and finish time columns.
many days ahead/behind the baseline we are at a given point. I was wondering
if there is a quick way to determine/calculate this figure. I have tried
several things, but wanted a sanity check on the best method.
Project info
I have set up the project so that everything rolls up to a single summary
line. Based on specific constraints, links, and durations inputed, the dates
are scheduled by Project. I have established a baseline and we are tracking
completion of individual tasks under the actual start and finish time columns.