A
AlisonH
I am looking after a large schedule involving a number of sub-projects. Each
week, the leads of each sub-project update their percentage complete on the
Gantt chart. The director now wants to know exactly how the rolled-up
percentage complete compares to where we should be if every task was
progressing exactly as planned (which as we all know, never happens)!!
I thought that I had to enter the % work complete, and then go to the
Tools/Tracking/update project menu item to update the % complete (if
everything were on track). However, this seems to update both.
I can't seem to find anything that adequately explains the differences
between the % complete and % work Complete fields, and why they are sometimes
different and sometimes the same.
week, the leads of each sub-project update their percentage complete on the
Gantt chart. The director now wants to know exactly how the rolled-up
percentage complete compares to where we should be if every task was
progressing exactly as planned (which as we all know, never happens)!!
I thought that I had to enter the % work complete, and then go to the
Tools/Tracking/update project menu item to update the % complete (if
everything were on track). However, this seems to update both.
I can't seem to find anything that adequately explains the differences
between the % complete and % work Complete fields, and why they are sometimes
different and sometimes the same.