% Complete vs % Work Complete

J

Jrufin

Hi,
I have a summary task saying "99% Complete" and "100% Work Complete"? All
work is already done how come the overall % complete is still showing 99% ?
 
D

Dave

Jrufin said:
Hi,
I have a summary task saying "99% Complete" and "100% Work Complete"? All
work is already done how come the overall % complete is still showing 99% ?

Do you have any milestones under the summary task? You have to manually
set them to 100% complete.
 