Here is the situation:
1. Resource has updated his Task completion % using PWA,
PM is notified, PM has accepted the change, the Project
plan shows updated % completed
2. Go to PWA , using Project View, PM finds that %
completion is still at 0%.
I have tried Colloborate -> Publish ->ALL ( also New and
Changed , Publish Project Plan, Republish Assignment ).
But PWA view shows the task at 0% but the Project server
shows 100% complete.
What gives ?
1. Resource has updated his Task completion % using PWA,
PM is notified, PM has accepted the change, the Project
plan shows updated % completed
2. Go to PWA , using Project View, PM finds that %
completion is still at 0%.
I have tried Colloborate -> Publish ->ALL ( also New and
Changed , Publish Project Plan, Republish Assignment ).
But PWA view shows the task at 0% but the Project server
shows 100% complete.