% completed not updated in PWA view

R

Ramesh

Here is the situation:

1. Resource has updated his Task completion % using PWA,
PM is notified, PM has accepted the change, the Project
plan shows updated % completed

2. Go to PWA , using Project View, PM finds that %
completion is still at 0%.

I have tried Colloborate -> Publish ->ALL ( also New and
Changed , Publish Project Plan, Republish Assignment ).

But PWA view shows the task at 0% but the Project server
shows 100% complete.

What gives ?
 
R

Ramesh

How do I get it uncached ? If its some sort of caching
issue I expect it to be uncached within 24 hrs or a reboot
or something but this is persistent. Couple of weeks later
its still not showing the % completions.
 
G

Gary Chefetz [MVP]

Ramesh:

Are there errors in the application log? Are there files backed up in the
ViewDrop folder?

--
Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 