CompleteThrough

A

andrewandrew

CompleteThrough seems to be an available value for the display of Gantt bars,
but I can't find the field. What exactly is the CompleteThrough object? Is
there any way I can use it in filters? In particular, I would like to find
work that is complete through a date in the future, as such tasks have
completed work that is scheduled in the future and that is taking away from
my available resources.

Andrew
 
G

Gérard Ducouret

Andrew,

Actually, the CompleteThrough field is not accessible. But you can use the
"Stop" which gives a similar result.

Gérard Ducouret
 
A

andrewandrew

Thanks, Gerard. The Stop field does just what I want. How many of these
inaccessible fields are there? Any idea why they are inaccessible?
 