J
Junkyard Engineer
I have a big schedule (> 1000 tasks). I want to simplify the Project Summary
and I have done a Project Dash Board in Excel which follows 4 major
parameters : Budget, Schedule, Quality, Other (multivariate). Each are
attributed a value of 1 to 9 depending on the level of risk so 3 colors are
used grren, yellow and red.
In MSP, I want to assign this "risk level" manually (or automatically based
on some criteria: how do we do that?). So, I thought of adding a text column
where I can put my evaluation of the risk level.
From there, since we cannot do conditionnal formatting as in Excel to change
colors of tasks, I thought I would export only those task that are critical
(i.e. Risk level > 6 or only milestones with their current completion level)
and apply conditionnal formating in Excel to change the colors and treat the
information appropriately for my Dashboard.
Is it possible to do the part in MSP ?
Tia
and I have done a Project Dash Board in Excel which follows 4 major
parameters : Budget, Schedule, Quality, Other (multivariate). Each are
attributed a value of 1 to 9 depending on the level of risk so 3 colors are
used grren, yellow and red.
In MSP, I want to assign this "risk level" manually (or automatically based
on some criteria: how do we do that?). So, I thought of adding a text column
where I can put my evaluation of the risk level.
From there, since we cannot do conditionnal formatting as in Excel to change
colors of tasks, I thought I would export only those task that are critical
(i.e. Risk level > 6 or only milestones with their current completion level)
and apply conditionnal formating in Excel to change the colors and treat the
information appropriately for my Dashboard.
Is it possible to do the part in MSP ?
Tia