R
Renata
Hi again ,
I also am new to this group and ms project.
I just was wondering if someone could confirm if I have
applied the correct logic.
I have a project where I have changed the working week
hours to 30 and changed the working day to 6 hours ( as
I believe 1 hour of the day is unproductive and should be
counted. Our standard work week is 35 hours @ 7 hours per
day.
So when I assign a resource to a task at 30% , I assume
that this translates that the resource is able to work on
the task 30% of the 6 hours , ie 1.8 hours .
am I correct ?
Many thanks again,
Renata
I also am new to this group and ms project.
I just was wondering if someone could confirm if I have
applied the correct logic.
I have a project where I have changed the working week
hours to 30 and changed the working day to 6 hours ( as
I believe 1 hour of the day is unproductive and should be
counted. Our standard work week is 35 hours @ 7 hours per
day.
So when I assign a resource to a task at 30% , I assume
that this translates that the resource is able to work on
the task 30% of the 6 hours , ie 1.8 hours .
am I correct ?
Many thanks again,
Renata