convert work resource to material resource?

R

Riko Wichmann

Dear all,

in our project plans we also do capital investment planning, where the
resource "invest" is of type material with a rate of 1 kEuro.

However, I happened that some people did not pay attention and planned
also their investments as work with 100% = 100 kEuro. (why anyone would
do that without at least asking someone is beyond me!)

Is there a way to convert those work resources to material resources
keeping the above correspondence?

When I just change the type of the resource to material and set the rate
to 1 kEuro, it seems like it uses something like 100% = 0.01 = 0.01
kEuro. I cannot set the rate to 100 kEuro because it would clash with
other plans.

Any ideas?

Thanks a bunch,

Riko
 