I would like to assign resources to a task, and be able to copy the resource
allocation to another task. If I copy from the resource column in the task
list, it allocates the work evenly to the resources. But, I don't want the
work allocated evenly, I want it allocated exactly as it was allocated in the
task I am copying from.
 
G

Gérard Ducouret

Hello Walter,

You can copy the work load from a task to another in the Resource Usage or
in the Task Usage view.
Problem : take care of the week ends if the tasks are not positionned on the
same dates on the timescale.

Gérard Ducouret
 