Sorry, I really don't understand how you have this set up. Can you
provide
more details?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
I agree with you, but IÃ,´m using the calculate option: The Ms Project
do
not
calculate the actual cost, so if I informe % concluded and my actual
cost
=
0, so the cost = remaining cost, beacuse cost = remaining cost + actual
cost.
But my problem is:
Exemple:
Activity 1
50% concluded
Baseline Cost = 4000
Actual Cost = 2000
Initial Date = 01/01/06
End Date = 03/05/06
Actual Date = 31/03/06
Work Fixed Task Type
Go to resource view (cost and actual cost by month) In Feb I have
remaining
cost!!! I expected Ms Project would allocate the remaining cost in Apr.
Could you please simulate this? I will appreciate.
Thanks a lot.
PriKobo
"Steve House [Project MVP]" escreveu:
So on the last date of the task the remaining cost is the total
cost???
This really doesn't make a lot of sense. Remaining Cost is Cost minus
Actual.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
If IÃf,Ã,´m not using the Actual Cost, Cost field is the Remaining
Cost,
but I
would like to see the remaining cost distributed after the Actual
Date
in
the
Resource Usage View (the % concluded bar is before the actual date).
Has anyone the solution to this problem?
Many thanks