I'm trying to understand if it is possible to view the History of the
cost...
I'd like to view, for example, one month ago how much I have spent
and... or maybe in the future....
Something like a cash flow...
I need this, because, combining Project to the Accounting system, I
can understand on the ongoing, how much will cost the project...
Here you are an example:
with the accounting system, I can be sure that until 1 week ago I have
spent $ 100.000...
with project, I'd like to know (based on the same date - 1 week ago!)
how much is the remaining costs....
in this case my prevision should be more accurate: 100.000
(accounting) + Remaining Cost (project)...
thanks to everybody
Vit
I'm trying to understand if it is possible to view the History of the
cost...
I'd like to view, for example, one month ago how much I have spent
and... or maybe in the future....
Something like a cash flow...
I need this, because, combining Project to the Accounting system, I
can understand on the ongoing, how much will cost the project...
Here you are an example:
with the accounting system, I can be sure that until 1 week ago I have
spent $ 100.000...
with project, I'd like to know (based on the same date - 1 week ago!)
how much is the remaining costs....
in this case my prevision should be more accurate: 100.000
(accounting) + Remaining Cost (project)...
thanks to everybody
Vit