Cost per task and per resource

L

Lars Aurdal

Hi,

Three resources work on my project. In my Gantt diagram I would like to
introduce a column for each resource showing how much that particular
resource costs in relation to each task. I'm sure this can be done but
finding the right varaibles and functions is beyond me. Any ideas?

Lars
 
J

Jan De Messemaeker

Hi Lars,

To show it in the Gantt Chart will require some VBA programming, but it is
readily available in the task usage view: insert the cost column.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top