Create new task calendar - no working days in Jul & Aug

M

M

How can I force a task or project to have no working days in July & August.

The calandar says "You must have at least one working day in the calendar."
 
G

Gérard Ducouret

Hello,
If you selected all the 7 columns of the Calendar (From the S of Sunday to
the M of Monday) , and clicked Non Working time option, you selected all the
days until december 2049.
That would be a good calendar for tired resources, but as you saw, Project
rejected it ;-(

Gérard Ducouret

M said:
How can I force a task or project to have no working days in July & August.

The calandar says "You must have at least one working day in the
calendar."
 
G

Gérard Ducouret

..../..
I forgot to say that you must select week row by week row

Gérard Ducouret

M said:
How can I force a task or project to have no working days in July & August.

The calandar says "You must have at least one working day in the
calendar."
 
J

Jan De Messemaeker

Hi M,

I'm sorry, that is not the case when you select all the days in Julmy, then
in August to declare them nonworking tilme
But when you select all the day headers (Mo-Fri) that is valid from Jan1,
1984 till Dec 31, 2049, in other words forever. And you must have at mleast
one working day...
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
M said:
How can I force a task or project to have no working days in July & August.

The calandar says "You must have at least one working day in the
calendar."
 