Creating a custom formula with two peices of data

L

lazarus long

Hi, new project user here trying to figure out how to create a formula that
does what i want.

Rght now i have 'DateDiff("d",[Start],[Finish])+1' in the 'Text1' field to
show me the calander duration of a project.

I want this to also include the information in my Task Name collum, so I can
have the calander duration and the task name show in the top level roll up on
the Gnatt

How would i write this forumla?

thanks!
 
J

Jan De Messemaeker

Hi,

First, you cannot write a formula in the task name column itself, you will
have to write one in a text field
It could look like [Name] & [Text1]
HTH
 
L

lazarus long

Thanks, got the formula i need. Is there a way i can insert a space between
[Name] & [Text1]?
 