C
caffo
I need to input a generic schedule that depicts timeline milestones after
receipt of an order. I have been unable to find a way to do this without
using a normal calendar. For instance, I could have the following:
Receipt of order - day 0
Receipt of components - day 50
Complete Manufacturing - Day 100
Customer acceptance testing - Day 110
Shipment - Day 120
ETC.
Can project do this? Or is this a Visio or other program task? Thanks.
receipt of an order. I have been unable to find a way to do this without
using a normal calendar. For instance, I could have the following:
Receipt of order - day 0
Receipt of components - day 50
Complete Manufacturing - Day 100
Customer acceptance testing - Day 110
Shipment - Day 120
ETC.
Can project do this? Or is this a Visio or other program task? Thanks.