B
Barry
I want to create a Project schedule that does not have specific
calendar dates on it. I would prefer that it display delta time (day
1, day 2, week 1, week 2, etc). Now I know how to make the timeline
show the gantt chart with these headers, but the program itself still
wants a calendar start date and still wants tasks to begin on specific
dates based on the calendar.
Is there any way to get the program to work other than cheating a
start date and other calendar dates to get the result?
Thanks,
Barry
calendar dates on it. I would prefer that it display delta time (day
1, day 2, week 1, week 2, etc). Now I know how to make the timeline
show the gantt chart with these headers, but the program itself still
wants a calendar start date and still wants tasks to begin on specific
dates based on the calendar.
Is there any way to get the program to work other than cheating a
start date and other calendar dates to get the result?
Thanks,
Barry