Critical Milestones

T

Tracey

Is there that a milestone can automatically be shown as critical on the Gantt
Chart, if the milestone shows a negative total slack?
Thanx
 
T

Trevor Rabey

In the default Gantt Chart View, where the bar formatting is kept,
Milestones display as black even if they are Critical (Total Slack <= 0),
and even if you have run the Gantt Chart Wizard to show Critical Tasks.
Suggestion: leave the default Gantt Chart as it is, make a copy of it (View,
More Views etc), with a distinctive name like "AAA special Gantt Chart
number 1", and format its bar styles (Format, Bar Styles). Go down the list
to the black diamond for the Milestones and add another row below that.
Define the style, Name = Critical Milestone, definition is
"Milestone,Critical".

Trevor
 
T

Tracey

Thanx so much!
--
Regards
Tracey


Trevor Rabey said:
In the default Gantt Chart View, where the bar formatting is kept,
Milestones display as black even if they are Critical (Total Slack <= 0),
and even if you have run the Gantt Chart Wizard to show Critical Tasks.
Suggestion: leave the default Gantt Chart as it is, make a copy of it (View,
More Views etc), with a distinctive name like "AAA special Gantt Chart
number 1", and format its bar styles (Format, Bar Styles). Go down the list
to the black diamond for the Milestones and add another row below that.
Define the style, Name = Critical Milestone, definition is
"Milestone,Critical".

Trevor
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top