H
Helen
Hi,
I'm using Project 2002.
I've got a series of tasks, with a lot of dependancies, and a resources of 2
man days performing the tasks. I have leveled the tasks so that the resources
are not overallocated and have then asked Project to show me the critical
path, expecting the series of red (instead of blue) bars to always finish and
start as the pervious tasks finished and started. Instead, alot of my
dependancy arrows ahve turned red, but only 3 of my 22 bars have turned red.
There appears to be a lot of time between these tasks which has not been
considered to be on the critical path. I'm quite confused as to what is
wrong. I even started again incase I'd put a strange dependacy in which would
cause this, but can see nothing. Any thoughts?
Thanks
Helen
I'm using Project 2002.
I've got a series of tasks, with a lot of dependancies, and a resources of 2
man days performing the tasks. I have leveled the tasks so that the resources
are not overallocated and have then asked Project to show me the critical
path, expecting the series of red (instead of blue) bars to always finish and
start as the pervious tasks finished and started. Instead, alot of my
dependancy arrows ahve turned red, but only 3 of my 22 bars have turned red.
There appears to be a lot of time between these tasks which has not been
considered to be on the critical path. I'm quite confused as to what is
wrong. I even started again incase I'd put a strange dependacy in which would
cause this, but can see nothing. Any thoughts?
Thanks
Helen