Critical Path View

D

Diederick

Hi,

I am currently busy buidling a relatively large and long a project which
makes it difficult to view the whole project on the PC screen. If I change
the view to show the critical path, only the bars in the Gantt chart change
to red. I would appreciate it if someone could help me to change the colour
of the tasks in the critical path as well (the wording in the task name
spreadsheet column), if this is possible. By having this, I would be able to
see which tasks is on the critical path by just looking at the list of tasks.
This is also very helpfull when you print the project.

Best Regards
Diederick
 
J

Jim Aksel

Easily accomplished Diederick!

Format/Text Styles....
A new window opens. In the Item to Change drop box, select Critical Tasks.
Change the font name, font style, size, underline, and color as desired.
Click OK.
-
If this post was helpful, please consider rating it.

Jim

Check out my new blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top