M
Michele
In the link http://office.microsoft.com/en-us/assistance/HA010211731033.aspx
i found this definitions of critical tasks:
A task becomes critical when it meets any one of the following conditions:
It has no slack.
It has a Must Start On (MSO) or Must Finish On (MFO) date constraint
(constraint: A restriction set on the start or finish date of a task. You can
specify that a task must start on or finish no later than a particular date.
Constraints can be flexible [not tied to a specific date] or inflexible [tied
to a specific date].).
It has an As Late As Possible (ALAP) constraint in a project scheduled from
a start date.
It has an As Soon As Possible (ASAP) constraint in a project scheduled from
a finish date.
It has a finish date that is the same as or beyond its deadline (deadline: A
target date indicating when you want a task to be completed. If the deadline
date passes and the task is not completed, Project displays an indicator.)
date.
A task stops being critical when it's marked as completed, because it then
can no longer affect the completion of successor tasks or the project finish
date.
Seen what's above i don't understand why, if i create a new project
scheduled from the end date and i create a task that has an As Soon As
Possible (ASAP) constraint , Project doens't indicate me that task as a
critical task.
Thanks in advice for any help.
Michele
i found this definitions of critical tasks:
A task becomes critical when it meets any one of the following conditions:
It has no slack.
It has a Must Start On (MSO) or Must Finish On (MFO) date constraint
(constraint: A restriction set on the start or finish date of a task. You can
specify that a task must start on or finish no later than a particular date.
Constraints can be flexible [not tied to a specific date] or inflexible [tied
to a specific date].).
It has an As Late As Possible (ALAP) constraint in a project scheduled from
a start date.
It has an As Soon As Possible (ASAP) constraint in a project scheduled from
a finish date.
It has a finish date that is the same as or beyond its deadline (deadline: A
target date indicating when you want a task to be completed. If the deadline
date passes and the task is not completed, Project displays an indicator.)
date.
A task stops being critical when it's marked as completed, because it then
can no longer affect the completion of successor tasks or the project finish
date.
Seen what's above i don't understand why, if i create a new project
scheduled from the end date and i create a task that has an As Soon As
Possible (ASAP) constraint , Project doens't indicate me that task as a
critical task.
Thanks in advice for any help.
Michele