Cum Work changing

J

Jon Smith

I have a project plan that the Cum Work values will change as you move around
in the Timescale portion of the view. If you set your cursor on a particular
week so that week is the last week (we're using weeks as the display)
displayed, then either arrow or mouse click to at least 2 later weeks, then
return to the week in question, then the week after the week in question now
shows the value of the week in the Cum Work field you were just looking at
instead of its correct value.

If you arrow or click on another field in the Timescale portion, you will
see the Cum Work value change to the correct value.

Tried it on both Project 2002 and 2003, same problem in both, same problem
on multiple computers, same problem on multiple LAN's.

Anyone have a guess as to what is causing this?