R
RobH
Hello,
I want to add a custom cost field to capture the original cost estimate for
each control account at the control account level . This would be used as a
reference point to compare the original cost estimate to the planned and
actual costs based on the deliverables and assignments within each control
account. I would like this custom cost estimate to roll up to the higher
summary levels in the schedule, but cannot get the custom field to sum to
higher levels or to the project total level. Any suggestions appreciated.
Thanks,
Rob H.
I want to add a custom cost field to capture the original cost estimate for
each control account at the control account level . This would be used as a
reference point to compare the original cost estimate to the planned and
actual costs based on the deliverables and assignments within each control
account. I would like this custom cost estimate to roll up to the higher
summary levels in the schedule, but cannot get the custom field to sum to
higher levels or to the project total level. Any suggestions appreciated.
Thanks,
Rob H.