K
KingKikapu
Is there any way to get a custom cost column to work at the resource
ASSIGNMENT level? In the resource usage view, I can add a custom cost
column and fill the assignments with costs, but the field will not roll
up to the resource summary line. I would really like to be able to roll
up these costs. I would also really like to be able to add 2 or 3
custom costs columns together at the assignment level and put the
results in a new custom cost field that would also be able to rollup to
the resource summary level. Would setting the calculation mode to
manual help?
Is there anyway to do this? Is VBA my only option? If it is, I do not
know much VBA at all; could someone please point me in the right
direction?
Thanks in advance.
ASSIGNMENT level? In the resource usage view, I can add a custom cost
column and fill the assignments with costs, but the field will not roll
up to the resource summary line. I would really like to be able to roll
up these costs. I would also really like to be able to add 2 or 3
custom costs columns together at the assignment level and put the
results in a new custom cost field that would also be able to rollup to
the resource summary level. Would setting the calculation mode to
manual help?
Is there anyway to do this? Is VBA my only option? If it is, I do not
know much VBA at all; could someone please point me in the right
direction?
Thanks in advance.