Hi,
Let's first talk about the budget cost field.
Historically, in MS Project's (and many people's) philosophy the "budget"
must be the same thing as the "baseline" - the estimate at project start
time.
The idea is that a budget must be made bottom up, and the project manager
sets his own budget.
The problem is that I never worked in, with nor for an organisation that
works this way. The budget is set by Big Brother and the project manager is
asked to find solutions fitting within that budget.
In that respect, however, it is logical that the budget is set at project
level - generally Big Brother doesn't care about the deatils, that is the
PM's problem.
Then to your first question. What might be an "adjusted Cost field" at task
and assignment level? In no project management method have I heard about
that... thus if it isn't defined, Project will not supply it. If you give me
a definition, I can think of a method (most likely VBA procdure) to
calculate it, but franly, adjust cost values depending on the budget... I do
not see that easily.
Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf