Custom Months

M

Mike

Is there a way in Project 2000 to create a calendar with
custom months? We run based on a calendar of either 4-
or 5-week months.

Thanks!
 
J

John

Mike,
Unfortunately no. No version of Project can handle accounting months. It
can be done however. I have written a couple of VBA macros that do
exactly what you want - work with a 4-4-5 accounting month calendar. The
macros are not freeware but if you are interested, write me direct.

John
 