I will be needing to create a project binder of all tasks to an invidual
resource (primary & backup). Is there a way in project that I can create this
custom report by filtering on that person for all of his/her primary and
backup tasks.

I figured it something similar for a minute but forgot how I got to that
screen.

Thank you in advance!
 
J

John

VH said:
Hi,

I will be needing to create a project binder of all tasks to an invidual
resource (primary & backup). Is there a way in project that I can create this
custom report by filtering on that person for all of his/her primary and
backup tasks.

I figured it something similar for a minute but forgot how I got to that
screen.

Thank you in advance!

VH,
You don't say what information you need in the report but the Resource
Usage view will give the basic information. Filter on the resource name
to get an individual report for each resource or simply insert a manual
page break between resources (if the goal is a hardcopy report).

Hope this helps.
John