K
ken
Hello,
I have been trying to generate a report based on the
timesheets that users enter using Project Server. The
reports I've been trying to get are a "hours worked per
day" report. I have set up a filter to help do this but I
have not been able to figure out how to get the tasks
filtered properly.
Essentially I've been using the Actual Work field (greater
than zero compare) and the Actual Start and Actual Finish
fields (for a specified date range). However, these field
values only check the information for the entire task, not
the day(s) within the specified range.
So what I am looking for is a report that shows which
tasks the resource worked on (and how many hours) within a
specified date range. Not all of their tasks and
independant of the start and end dates of the task. And
only showing the time they worked on the task within that
range.
Any hints someone might have would be appreciated.
Thank-you,
Ken Lee
I have been trying to generate a report based on the
timesheets that users enter using Project Server. The
reports I've been trying to get are a "hours worked per
day" report. I have set up a filter to help do this but I
have not been able to figure out how to get the tasks
filtered properly.
Essentially I've been using the Actual Work field (greater
than zero compare) and the Actual Start and Actual Finish
fields (for a specified date range). However, these field
values only check the information for the entire task, not
the day(s) within the specified range.
So what I am looking for is a report that shows which
tasks the resource worked on (and how many hours) within a
specified date range. Not all of their tasks and
independant of the start and end dates of the task. And
only showing the time they worked on the task within that
range.
Any hints someone might have would be appreciated.
Thank-you,
Ken Lee