A
andy
hope someone can advise,
I have inherited a project that has 200 ish tasks that have a start date for
the basline first task only.
the remainder of the tasks are either +/- start and finsih dates for each
task against the baseline in months.is there a simple formulae that i can
apply to determine the start and finish dates rather than sit here with a
calendar. ( i've never written a macro so wouldnt know how to start)
any help would be grateful
andy
I have inherited a project that has 200 ish tasks that have a start date for
the basline first task only.
the remainder of the tasks are either +/- start and finsih dates for each
task against the baseline in months.is there a simple formulae that i can
apply to determine the start and finish dates rather than sit here with a
calendar. ( i've never written a macro so wouldnt know how to start)
any help would be grateful
andy