More than likely the task type is fixed duration.
Advice: Do not key in dates.
Set a project start date (Project/Project Information...)
Type in your task names.
Key in durations (default is days but this can be changed).
Establish relationships between the tasks by linking tasks, that is "What
must be done before I can start this task?" Tasks can be linked by
highlighting the the tasks involved and clicking the link icon (looks like a
chain link). As an alternative (this is what I do), key in the task ID
number into the predecessor column.
If you type in dates, you set constraints in the software that force the
program to honor the dates. Gernerally, a keyed date overrides schedule
logic for the linking. Therefore, a keyed date ruins the schedule logic and
defeats the entire purpose of the program.
--
If this post was helpful, please consider rating it.
Jim
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project