B
BenL712
Let me preface this by saying I know this is not the correct way to use the
full power of Project. However, I'm working in an organization that is
nowhere close to using any sort of project/time tracking, and I would like to
start getting people used to this.
I really like the way Project/Outlook handles email collaboration, with
tasks sent out and the ability to request updates. Does anyone know of a way
I can customize this feature so that instead of requesting hours
complete/remaining, I could have each task owner report percent complete /
estimated completion date?
I'm also assuming that I would have to have all the tasks set up as fixed
duration so that Project would handle the resource assignments and updates
correctly.
If anyone could point me in the right direction for this, I'd greatly
appreciate it. Thanks!
full power of Project. However, I'm working in an organization that is
nowhere close to using any sort of project/time tracking, and I would like to
start getting people used to this.
I really like the way Project/Outlook handles email collaboration, with
tasks sent out and the ability to request updates. Does anyone know of a way
I can customize this feature so that instead of requesting hours
complete/remaining, I could have each task owner report percent complete /
estimated completion date?
I'm also assuming that I would have to have all the tasks set up as fixed
duration so that Project would handle the resource assignments and updates
correctly.
If anyone could point me in the right direction for this, I'd greatly
appreciate it. Thanks!