I am interested in creating a Resource REport that I can filter by date and
specific resource. I tried basing the report off of the Who does What
report, which is the way I want it to appear, but I would like to filter for
tasks that are not completed and fall withing my date range. Unfortunately,
it shows tasks outside of my date range. If I have a task that is in July
09, it should not show in a March to April report. Am I using the wrong
fields in my filter?
I am using REsource ID as a parameter, Finish and Start for date parameters,
% Work Complete as less than 100% . Also, I would like to run the report so
that it spits out a new page(s) for each resource rather then running
individual reports. Any help would be appreciated.
 