Customizing the task Information dialog box, Predecessors tab

D

dhardy

Hi-
Is there a way to add a column to the predecessor table? I would like to
add finish date so I can see what is holding up the task. Thanks.
 
G

Gérard Ducouret

Hi,

Sorry, you can't customize the Task Information dialog.

Gérard Ducouret
 
M

Mike Glen

Hi dhardy ,

Welcome to this Microsoft Project newsgroup :)

Sorry, there's no way to change the Task Information form :( I suppose it
might be possible to create you own form via vba. If you're interested, try
posting on the developer newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top