Hi,
I have a series of activities which are following each other.
I linked the first one (lets call it a) to another activity that is
earlier(lets call it d).
When postponed a after d's start date it postponed d and its followers.
So far so good.
When I erased the connection between a & d, d went back to its original
date, the "start no earlier than" date.
My question is, how can I make d's "start no earlier date" stay where it is
now (after it got postponed) and not go back to its orginal date?
Thanks,
Assaf
I have a series of activities which are following each other.
I linked the first one (lets call it a) to another activity that is
earlier(lets call it d).
When postponed a after d's start date it postponed d and its followers.
So far so good.
When I erased the connection between a & d, d went back to its original
date, the "start no earlier than" date.
My question is, how can I make d's "start no earlier date" stay where it is
now (after it got postponed) and not go back to its orginal date?
Thanks,
Assaf