Date Formatting in Project 2002

J

Jerome Ranch

Project displays task start and finish date in the task pane with
Tue 4/1/2006, for example. I only want the date without the day
(4/1/2006). How do I format that?
Thanks
Jerry
 
J

Jan De Messemaeker

Hi,

Tools, Options, View, in Date Format select any format you want.
HTH
 