I am working on a project in which I need to provide dates to the same
recurring set of tasks for different classes. The dates need to be a week
before training delivery or 2 weeks before 4 weeks before etc. Is there some
way that I can customize the task to provide dates in this fashion?
 
J

JulieS

Hello Gina,

Have you tried a start to start link with a lead between the training
delivery task and the other tasks?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 