I have around 500 activities in one consolidated project ( which
consists of 5 inserted projects). I am trying to find the work or
resources scheduled for 10 days ( or less or more where range of days
to be specified by end-user) after levelling or w/o levelling.
I tried various reports, even tried to customise report. The day-wise
report in this cases goes to 258 to 550 pages. All reports are giving
report from first day ( in this case 10-08-05 ) till last day of
schedule ( 27-03-07 ), whereas I want only 10 days ( or less or more )
report.
Please suggest a solution, Thanks in advance. & Happy new year to all.
consists of 5 inserted projects). I am trying to find the work or
resources scheduled for 10 days ( or less or more where range of days
to be specified by end-user) after levelling or w/o levelling.
I tried various reports, even tried to customise report. The day-wise
report in this cases goes to 258 to 550 pages. All reports are giving
report from first day ( in this case 10-08-05 ) till last day of
schedule ( 27-03-07 ), whereas I want only 10 days ( or less or more )
report.
Please suggest a solution, Thanks in advance. & Happy new year to all.