Good morning,
I have a file I'm working with where there's a summary task that includes 3
sub-tasks. Two of these sub-tasks have a duration of 1 day and the 3rd has 6
days. However, on this 3rd task, the start date is 3/30/05 and the finish
date is 7/13/06, giving the summary task an overall 339 days of duration!
I've gone thru the project, selected all tasks and set all to start "as soon
as possible", as well as using the analysis bar to adjust dates. Short of
changing the finish date, or re-creating the file, is there something I can
do to correct this?
Many thanks, in advance...L
I have a file I'm working with where there's a summary task that includes 3
sub-tasks. Two of these sub-tasks have a duration of 1 day and the 3rd has 6
days. However, on this 3rd task, the start date is 3/30/05 and the finish
date is 7/13/06, giving the summary task an overall 339 days of duration!
I've gone thru the project, selected all tasks and set all to start "as soon
as possible", as well as using the analysis bar to adjust dates. Short of
changing the finish date, or re-creating the file, is there something I can
do to correct this?
Many thanks, in advance...L