M
Mary Ann
When I add a deadline marker to my End Project milestone and set the deadline
date as the end project date + 2, there is no longer a critical path. I
understand this is because the tasks now have total slack.
When I add a deadline marker to a task which is on the critical path, say
half way through the project, the critical path remains. Following the logic
of the example above, I would have thought the earlier tasks would now have
total slack and therefore not show a critical path for that part of the
project.
When do deadline markers impact the critical path and when not?
date as the end project date + 2, there is no longer a critical path. I
understand this is because the tasks now have total slack.
When I add a deadline marker to a task which is on the critical path, say
half way through the project, the critical path remains. Following the logic
of the example above, I would have thought the earlier tasks would now have
total slack and therefore not show a critical path for that part of the
project.
When do deadline markers impact the critical path and when not?