B
bari_sax
I have a project that is running a bit behind schedule for a given deadline.
Almost all the tasks have some negative slack, and therefore the critical
path is shown for multiple parallel paths, even though some of these have
less "negative" slack than others. This makes it hard to find the wheat in
the chaff.
What I'd like to do is highlight the "most critical" path, namely the tasks
that have the most negative total slack. This will help us target the key
tasks that will bring us closer to deadline. Is there a way to display this?
(Perhaps by flagging those tasks that all tie for the maximum negative total
slack, then formatting the bar styles to pull out this flag?)
Almost all the tasks have some negative slack, and therefore the critical
path is shown for multiple parallel paths, even though some of these have
less "negative" slack than others. This makes it hard to find the wheat in
the chaff.
What I'd like to do is highlight the "most critical" path, namely the tasks
that have the most negative total slack. This will help us target the key
tasks that will bring us closer to deadline. Is there a way to display this?
(Perhaps by flagging those tasks that all tie for the maximum negative total
slack, then formatting the bar styles to pull out this flag?)