diddy_david
I have created a new calendar and change the working times to 07:30-16:30. I
have allocated this as the project calendar and assigned to to the Gantt
chart. I have also set the default start time and end time to reflect these
times. Then why is it the the Gantt chart shows tasks begining at 8am and
when calculating work in only calculates 7.5 hours?