2 usability questions:

1. Is there a way to set any new tasks added to the project to a default
value other than 500? I like to have new tasks as priority 1 as way for me
to know that they have not be set against other tasks.
2. Does project track the actual date a task was created somewhere? Is
there a way to write a script or something to do that, or do I just need to
manually enter it into a custom field (Text1, for example)? I want to know
the history of when a task was added to the project to help identify the
newest added features or requests for the project.

Thanks


Andy
 
J

Jan De Messemaeker

Hi Andy,

There is good news and there is bad news.
For Q1 the answer is soory, no way.

For Q2: The "Created" field is there for the taking!
HTH
 