Deliverables and Milestones

F

Figen

Hi there,

Could someone tell me the difference between those two and how do I mark the
deliverable on the project plan.

Thank you

Regards

Figen
 
P

Prj_Mngr

A deliverable is something that people work on to finish the project - such
as a completed requirements document, or a test plan. A milestone is an
important point in time such as "contract signed", "project approved" etc,
and usually have zero duration

A milestone can be marked as such in project, the deliverables are the list
of tasks that have to be completed.
Hope this helps, or let me know if you need more info.
 