Dependencies are not scheduling tasks.

B

BF

I am having an issue with the dependencies - when I create a dependency, MS
Project 2007 is not scheduling task 2 after task 1. Any ideas?
 
W

wasonamit

If Task 2 has a Date Constraint that might be causing this issue.

Double click on the task2 > Advanced Tab > Change constraint to As Soon As
Possible
 
S

Steve House [MVP]

How are creating rhe dependency? What is it doing? Did you manually enter
any start/finish dates or set any constraints? Is recalculation set to
"auto?"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top