Determining new finish date when ahead of schedule.

J

Jim Stoaks

When a tasks work is behind schedule there is the option of rescheduling the
remaining work to start after the current status date. If there a
corresponding capability to reschedule the remaining work for the current
status date if the task is ahead of schedule?
 
J

Jan De Messemaeker

Hi,

That is automatic, unless you plan from finish date Work is always schedules
as soon as possible.
HTH
 
G

Gérard Ducouret

Hello Jim,
Have a look at the calculations options :
Tools / Options / Calculation
- Move end of completed parts after after status date back to status date
- Move start of remainning parts before status date forward to status date
NB : set these settings *before* entering traking data.
Hope this helps,

Gérard Ducouret
 
J

Jim Stoaks

Thanks Gerard, just what I wanted.

Gérard Ducouret said:
Hello Jim,
Have a look at the calculations options :
Tools / Options / Calculation
- Move end of completed parts after after status date back to status date
- Move start of remainning parts before status date forward to status date
NB : set these settings *before* entering traking data.
Hope this helps,

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top