Difference Between EAC and BAC

A

Aravind G

Hi,

I have heard about EAC and BAC in various sources but unclear about the
difference between them and the formula to calculate both. How is it related
to Cost and Schedule Variances?

Can anyone throw light on these please?
 
M

MrAlNather

Hi,

I have heard about EAC and BAC in various sources but unclear about the
difference between them and the formula to calculate both. How is it related
to Cost and Schedule Variances?

Can anyone throw light on these please?

Hi,

BAC (budget at completion) is the initial budget for the project. EAC
(estimate at completion) is a dynamic forecast of the cost of the
project at the end. It is dynamic because it is calculated according
to the CPI (cost performance index) of the project as follows; EAC =
BAC/CPI.

The CPI is a measure of the health of the project. Greater than 1 is
good (more work is being acomplished than the amunt of work being
spent), less than 1 is bad (less work work is being accomplished than
money being spent). CPI will change as the project progresses, thus
changing the EAC.

Now...CPI is calculated as follows; CPI = BCWP/ACWP. BCWP (Budgeted
Cost of Work Performed) is the "Earned Value". You credit activities
with a portion (0 - 100%) of the budgeted cost for the activity. ACWP
(Actual Cost of Work Performed) is how much you have spent to date,
broken down into the elements of the project (otherise known as actual
cost). By the way BCWS (Budgeted Cost of Work Scheduled) is the
timephased budget for the project, also known as planned value.

Hope this helps..
 
A

Andrew Lavinsky

What's confusing is that you have two fields which more or less state the
same data - but based on different assumptions:

EAC - is your best guess as to how much the project will cost assuming that
the risks you have had to date (as calculated in your CPI) continue at a
constant rate. The easy calculation for this is BAC / CPI, where CPI is a
measure of your work efficiency.

Cost - is your best guess as to how much the project will cost assuming that
the risks you have had to date do not continue.

So basically, all issues of padding aside, Cost is an optimistic outcome
for the project budget, while EAC is a bit more pessimistic estimate of the
project budget. EAC will only be meaningful if you are doing Earned Value
calculations in your project. Otherwise, you should probably just use the
Cost field.

BAC is your approved budget at completion. That should generally be the
same as your Baseline Cost.

The goal then is to track the EAC against your BAC to see what kind of cost
overruns are predicted on the project:

Variance at Completion = VAC, VAC = BAC - EAC, or VAC = Baseline Cost - EAC

Note that the Cost Variance field has a slightly different calculation:

Cost Variance = Cost - Baseline Cost

....which in some circumstances will give you the opposite of the VAC calculation.
If you're not using Earned Value, stick to the Cost Variance.

For all of these fields, you should ensure that you have the Project Summary
task displayed so as to see the rollup of the field data.

If you do plan to implement Earned Value, consult a local PM training group
to get trained on EVMS. After having done that, talk to practitioners of
EVMS in MS Project to get a feel for the challenges and opportunities of
using that method.

-A


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top