Different %-Complete Reported Between Timesheet & Project...

M

MichaelDBang

Hello,

I'm running into an issue with reporting time from my timesheet in my
Outlook Addin.

There is a task that I have assigned that has 16hrs baseline. I have
assigned 8hours yesterday and 2 hours today on the task, bringing the total
to 10. I have Specified "Remaining Work" to 4hours. I saved the work to
Project Server and have submitted it to the PM (which is me).

I accepted the updates from the timesheet and updated the project in Project
2007. However, the task now shows 13hours worked and 100% complete.

How on earth does that happen? :|

I have deleted the task and tried to reclaim the proper state with the same
results. Is there something horribly obvious about this process that I'm
overlooking?

Thank you,
Michael
 
M

MichaelDBang

OK.

Getting my feet under me here.

It looks like if you save a Baseline, and you add more tasks after the
Baseline was created, you're supposed to Set the Baseline for the new tasks.
Is this correct? Otherwise things get FUBAR'd.

I went ahead and set the Baseline to the new tasks that I added and that
seemed to restore expected times. Whew.

I just got my "book" in today and I do see a section related to Change
Control. Guess I should read that before posting on here. Oops. ;)

Thanks,
Michael
 